← back to the index
BB-011 combustible ACM cladding

Grenfell Tower — Combustible ACM Cladding Defeated Every Compartment in the Building

Death toll
72 killed (74 injured)
Structure
Grenfell Tower, 24-storey reinforced-concrete residential tower, North Kensington, London
Failed
14 June 2017
Status
Gutted

Summary

Grenfell Tower, a 24-storey reinforced-concrete residential block in North Kensington, west London, burned out almost entirely in the early hours of 14 June 2017, killing 72 people in a fire that began in a single fourth-floor kitchen and reached the roof in roughly half an hour. The concrete frame never fell — and that is the point. The structure did exactly what a concrete tower is designed to do; the failure was in the skin that a 2015–2016 refurbishment had wrapped around it. A combustible aluminium composite material (ACM) rainscreen, with an unmodified polyethylene core, carried flame up and across the entire facade in minutes and defeated the building's compartmentation completely.

This was not a structural collapse but a total compartmentation breach. Grenfell was built to the "stay put" principle: each flat is its own fire compartment, so a fire in one dwelling should be contained for long enough that the rest of the building can remain in place. That principle held for roughly fifteen minutes. The fire escaped Flat 16 through a uPVC window jamb into the newly installed external wall, found the polyethylene core of the cladding — a material with a heat of combustion comparable to petrol — and used the ventilated cavity behind the panels as a chimney. By 01:30 the fire had run to the crown of the tower; thereafter it spread back inward through dozens of flats at once, overwhelming the very compartmentation the stay-put strategy depended on.

The tower was completed in 1974 as part of the Lancaster West Estate. Its original concrete structure had no record of facade fire problems. The lethal change was retrofitted: an £8.6 million refurbishment, finished in 2016, that reclad the building in Arconic's Reynobond PE panels over Celotex RS5000 polyisocyanurate insulation — a combustible system on a high-rise, where the product literature and the regulatory guidance pointed the other way.

The Grenfell Tower Inquiry, chaired by Sir Martin Moore-Bick, did not treat the disaster as an accident. Its Phase 1 report (October 2019) found the ACM cladding was the "principal reason" the flames spread and that the external wall did not comply with the functional requirement of the Building Regulations. Its Phase 2 report (September 2024) found 72 deaths that were "all avoidable," the product of decades of failure by government and a construction-products industry marked by "systematic dishonesty." Grenfell has become the global byword for what a combustible facade does to a fire-safe building: it converts a contained kitchen fire into a death trap.

---

Timeline

1974
Tower completed
Grenfell Tower opens on the Lancaster West Estate, a 24-storey reinforced-concrete residential block of around 120 flats, designed on the cellular "stay put" compartmentation principle that each flat resists fire long enough to make whole-building evacuation unnecessary.
2012–2014
Refurbishment specified and value-engineered
A major refurbishment is planned for the ageing tower. The external cladding specification is changed from a zinc composite to a cheaper aluminium composite — Arconic's Reynobond PE — saving a reported sum on the contract while substituting a polyethylene-cored panel.
2014–2016
Combustible system installed
Reynobond PE rainscreen panels are fixed over Celotex RS5000 polyisocyanurate (PIR) insulation, leaving a ventilated cavity between insulation and panels. Both core and insulation are combustible; the assembly is never subjected to a passing full-scale BS 8414 system test as built.
May 2016
£8.6m refurbishment completed
The reclad tower is handed back. New uPVC windows are set within the cladding line, with gaps and detailing that connect each flat's interior to the combustible external wall cavity.
2013–2017
Residents warn of fire risk
The Grenfell Action Group repeatedly publishes warnings that the estate management is neglecting fire safety and that only a "catastrophic event" will expose the conditions. The warnings are not acted upon.
14 Jun 2017, ~00:50
Fire starts in Flat 16
A fault in a Hotpoint fridge-freezer ignites a fire in a fourth-floor kitchen. The first 999 call is logged at 00:54. Inside the flat the fire is ordinary and survivable.
14 Jun 2017, ~01:05–01:15
Fire escapes into the facade
Flame breaks out of the kitchen window into the external wall, ignites the polyethylene core of the ACM panels, and begins climbing the ventilated cavity by stack effect — escaping the compartment the building relied on.
14 Jun 2017, ~01:30
Fire reaches the roof
Within roughly 30–40 minutes the fire has run up the full height of the east face to the crown of the tower and begins spreading horizontally around the ACM architectural crown.
14 Jun 2017, ~01:30–04:00
Compartmentation fails inward
The external fire re-enters dozens of flats simultaneously through windows and the cavity, defeating compartmentation on multiple faces and floors at once. The London Fire Brigade maintains "stay put" until 02:47, far longer than conditions justified.
14 Jun 2017, by morning
72 dead, tower gutted
The fire burns for some 24 hours before it is brought under control; 72 people die and 74 are injured. The concrete structure survives; the interiors and facade are destroyed.
Oct 2019
Phase 1 report
The Inquiry finds the ACM cladding the principal cause of fire spread and the external wall non-compliant with the Building Regulations' fire requirement.
Sep 2024
Phase 2 report
The Inquiry attributes the 72 "avoidable" deaths to decades of state failure and "systematic dishonesty" by product manufacturers, and issues 58 recommendations.

The Build: A Fire-Safe Concrete Tower Wrapped in Fuel

Grenfell Tower's original 1974 structure was, in fire terms, sound. A reinforced-concrete frame with masonry-separated flats embodies the "stay put" doctrine that has underpinned British high-rise housing for half a century: each dwelling is a fire compartment rated to contain a fire for long enough that the building as a whole need not be evacuated. Concrete is non-combustible; the compartment walls and floors resist fire passage; a fire in one flat should burn itself out, or be extinguished, without ever threatening the flat next door, let alone the tower twenty storeys up. For forty years that is broadly how the building behaved.

The lethal property was introduced from the outside, late, and for cost. The 2012–2016 refurbishment added an over-clad external wall to improve the tower's thermal performance and appearance. The specified panel was changed from a fire-retardant or zinc-cored composite to Arconic's Reynobond PE — an aluminium composite material whose two thin aluminium skins sandwich a core of unmodified polyethylene, an ordinary thermoplastic with a heat of combustion the Inquiry later compared to petrol or diesel. Behind the panels sat Celotex RS5000, a combustible polyisocyanurate insulation board, and between insulation and panels ran a continuous ventilated cavity.

Three deficiencies were now stacked together. The cladding had a combustible core. The insulation behind it was combustible. And the cavity between them was a vertical flue, open from base to crown, that would draw a fire upward by stack effect once it took hold. The assembly as actually built was never validated by a passing full-scale BS 8414 facade fire test — the recognised route to demonstrate that an external wall on a tall building "adequately resists the spread of fire." The product literature for Reynobond PE itself stated the panel was suitable only for buildings up to about 10 metres. Grenfell was 67 metres. The building's defence against a contained kitchen fire had been quietly removed and replaced with an accelerant.

The Failure: How a Kitchen Fire Became a Facade Inferno

At around 00:50 on 14 June 2017, a fault in a fridge-freezer started a fire in the kitchen of Flat 16 on the fourth floor. This was a routine domestic fire; firefighters were on scene within minutes and, in any normally clad tower, it would have ended as a single-flat incident. Instead, flame reached the new uPVC window — set into the cladding line with detailing that bridged the flat interior to the external wall — and broke out into the facade.

What happened next was a textbook combustible-cladding fire, and it ran with extraordinary speed. The escaping flame ignited the polyethylene core of the ACM panels at the window head. Burning, the thermoplastic dripped and spread fire to the insulation and panels above; the ventilated cavity behind acted as a chimney, drawing air in at the base and venting hot gases at the top, so the fire climbed the cavity far faster than it could ever have spread across a non-combustible wall. Within roughly 30 to 40 minutes — by about 01:30 — the fire had reached the top of the 24-storey tower and was spreading horizontally around the building's ACM architectural crown, which the Inquiry singled out for causing the most rapid lateral spread.

The compartmentation breach then operated in reverse. A fire on the outside of the building is not contained by internal compartment walls at all; it re-enters the structure through whichever windows and cavities it reaches. From the facade, the fire broke back inward into flat after flat across multiple faces and floors simultaneously. The stay-put strategy — predicated on the fire staying inside one compartment — had been comprehensively defeated, yet the London Fire Brigade kept advising residents to stay in their flats until 02:47, when the building was already burning on every side. People who followed that advice were trapped above the fire. By the time the fire was controlled some 24 hours later, 72 people were dead. The concrete frame, meanwhile, stood. The killer was never the structure; it was the skin.

The Reckoning: An Inquiry That Named Dishonesty, Not Misfortune

The Grenfell Tower Inquiry, chaired by Sir Martin Moore-Bick, refused the vocabulary of tragic accident from the outset. Its Phase 1 report, published in October 2019, examined the night itself and reached an unambiguous engineering finding: the ACM panels with polyethylene cores were "the principal reason" the flames spread up the building so rapidly, behaving as a source of fuel with a heat of combustion akin to that of petrol. The external wall, the report found, did not comply with Requirement B4 of the Building Regulations, which demands that external walls adequately resist the spread of fire. The report also catalogued the failures of "stay put" and the absence of any plan to evacuate the tower once that strategy had collapsed.

Phase 2, published on 4 September 2024 after a six-year inquiry, traced the causes back through the supply chain and the state. Its roughly 1,700 pages concluded that all 72 deaths were avoidable and that the disaster was the culmination of "decades of failure" by central government and the construction industry. It found "systematic dishonesty" among the firms that made and sold the combustible products: manufacturers had manipulated fire-test evidence and marketing so that combustible cladding and insulation could be sold for use on high-rise buildings. The US manufacturer Arconic was found to have deliberately concealed the true fire performance of Reynobond PE; the insulation maker Celotex had described a passing test without disclosing the additional fire-resisting boards that made it pass. Every layer of defence — honest products, competent design, building control, regulatory guidance — had been allowed to fail in advance of the fire that exposed them. The Inquiry issued 58 recommendations, including a single construction regulator and licensing of high-rise contractors.

---

Contributing Factors

01
Combustible ACM cladding core
The Reynobond PE rainscreen had an unmodified polyethylene core with a heat of combustion comparable to petrol. Once flame reached it, the cladding became the principal fuel that carried fire up the entire facade. A non-combustible or genuinely fire-retardant core would have starved the external fire of its accelerant and kept a kitchen fire inside its compartment.
02
A ventilated cavity acting as a chimney
The continuous air gap between insulation and panels ran unbroken from base to crown, drawing the fire upward by stack effect and feeding it oxygen. Without effective cavity barriers to interrupt the flue at each floor, the cavity converted a local ignition into a full-height facade fire in minutes. Cavity barriers and compartmented cavities are precisely the detail that arrests this mechanism.
03
Combustible insulation compounding the load
Behind the panels, Celotex RS5000 polyisocyanurate insulation added a second combustible material to the external wall and contributed to vertical fire spread. Stacking a combustible insulant behind a combustible rainscreen multiplied the fuel available on the facade and the toxicity of the smoke. Mineral-wool or other non-combustible insulation removes this contribution entirely.
04
Total compartmentation breach by an external route
The building's entire life-safety strategy assumed fire would stay inside one flat. An external facade fire bypasses internal compartment walls completely, re-entering many flats at once through windows and cavities. The refurbishment introduced a fire path the stay-put doctrine had never contemplated, and nobody revalidated that doctrine against the new external wall.
05
A system never validated and a regulatory regime that let it pass
The wall as built was not proven by a passing full-scale BS 8414 test, product literature and guidance pointed away from combustible ACM on tall buildings, and manufacturers manipulated test and marketing evidence to sell it anyway. The physical hazard was knowable and, per the Inquiry, known; the missing element was honest products and enforced regulation before the fire arrived. ---

Aftermath

The Grenfell Tower fire killed 72 people and injured 74 — the deadliest residential fire in Britain since the Second World War — and it did so without toppling a single structural member. The Inquiry's Phase 1 report fixed the ACM cladding as the principal cause of fire spread and the external wall as non-compliant with the Building Regulations; Phase 2 found the deaths avoidable and the product industry "systematically dishonest." In the regulatory record the consequences were sweeping: the Building (Amendment) Regulations 2018 banned combustible materials in the external walls of new high-rise residential buildings in England, Approved Document B was overhauled, and the Building Safety Act 2022 created a Building Safety Regulator and a new dutyholder regime for higher-risk buildings. A national programme to identify and strip dangerous ACM and other combustible cladding from existing towers followed, exposing a remediation crisis still running years later. Grenfell itself stood gutted as evidence for years before demolition began in 2025. In the engineering and fire-safety literature the tower has become the global byword for a specific lethal pattern: a fire-safe structure given a combustible skin, a ventilated cavity left as a chimney, and a compartmentation strategy left unrevalidated against the wall that would defeat it.

---

Lessons

  1. Never place a combustible cladding or insulation on a building tall enough that the fire service cannot reach the top with water — on a high-rise, treat the external wall as part of the life-safety system, not as decoration.
  2. Revalidate the whole fire strategy whenever you change the facade; a "stay put" compartmentation plan is only as good as the assumption that fire cannot travel outside the building, and a new external wall can quietly void that assumption.
  3. Break every external cavity with effective cavity barriers — an unbroken ventilated gap behind cladding is a chimney that turns a local ignition into a full-height fire in minutes.
  4. Prove the wall you actually build with a full-scale system test, and distrust component marketing — a panel that passes in isolation, or a test described without its hidden fire-stops, tells you nothing about the assembly on the tower.
  5. When residents and product literature both warn that a system is unsafe for its height, escalate to enforced remediation — the documented warning is not a defence after the fire, it is the indictment. ---

References